Stories
Slash Boxes
Comments

SoylentNews is people

posted by Fnord666 on Monday October 02 2017, @02:05AM   Printer-friendly
from the testing-integration dept.

The launch of the James Webb Space Telescope has been delayed yet again:

The launch of NASA's James Webb Space Telescope (JWST) has been rescheduled to occur sometime between March and June 2019 from French Guiana. The delay follows a schedule assessment of the remaining integration and test activities that need to occur prior to launch. The JWST was previously scheduled to launch in October 2018. "The change in launch timing is not indicative of hardware or technical performance concerns," Thomas Zurbuchen, associate administrator for NASA's Science Mission Directorate at Headquarters in Washington, said in a NASA press release. "Rather, the integration of the various spacecraft elements is taking longer than expected."

The change in launch window request has been coordinated with the European Space Agency (ESA), which is providing the Ariane 5 launch vehicle for the JWST. As part of an agreement with ESA, NASA recently conducted a routine schedule assessment to ensure launch preparedness and determined that a reschedule was necessary.

While testing of the telescope and science instruments at NASA's Johnson Space Center (JSC) in Houston, Texas, continues to go well and remain on schedule, the spacecraft itself, made up of the spacecraft bus and sunshield, has experienced delays during its integration and testing at Northrop Grumman in Redondo Beach, California. "Webb's spacecraft and sunshield are larger and more complex than most spacecraft," said Eric Smith, program director for the James Webb Space Telescope at NASA Headquarters in Washington. "The combination of some integration activities taking longer than initially planned, such as the installation of more than 100 sunshield membrane release devices, factoring in lessons learned from earlier testing, like longer time spans for vibration testing, has meant the integration and testing process is just taking longer. Considering the investment NASA has made, and the good performance to date, we want to proceed very systematically through these tests to be ready for a Spring 2019 launch."

An upside? A better chance of being prepared to image Planet Nine during the 5-10 year operating life of JWST.

Also at NASA.


Original Submission

Related Stories

WFIRST Space Observatory Could be Scaled Back Due to Costs 9 comments

The Wide Field Infrared Survey Telescope (WFIRST) may have some of its capabilities scaled back due to overspending on the James Webb Space Telescope and the added cost of a coronagraph that was demanded by exoplanet researchers:

NASA will have to scale back its next big orbiting observatory to avoid busting its budget and affecting other missions, an independent panel says. The Wide Field Infrared Survey Telescope (WFIRST) is due for launch in the mid-2020s. But 1 year after NASA gave the greenlight its projected cost is $3.6 billion, roughly 12% overbudget. "I believe reductions in scope and complexity are needed," Thomas Zurbuchen, head of NASA's Science Mission Directorate in Washington, D.C., wrote in a memo that NASA released last Thursday.

Designed to investigate the nature of dark energy and study exoplanets, WFIRST was chosen by the astronomy community as its top space-based mission priority in the 2010 decadal survey entitled New Worlds, New Horizons in Astronomy and Astrophysics. But the start of the project was initially delayed by the huge overspend on its predecessor, the James Webb Space Telescope, which will be launched in 2019. Then last year, a midterm review of the 2010 decadal survey warned that WFIRST could go the same way and advised NASA to form a panel of independent experts to review the project.

[...] Zurbuchen's memo to Scolese directs the lab to retain the basic elements of the mission—the 2.4-meter mirror, widefield camera, and coronagraph—but to seek cost-saving "reductions." Hertz says this will require reducing the capabilities of instruments but ensuring they remain "above the science floor laid down by the decadal survey." The coronagraph will be recategorized as a "technology demonstration instrument," removing the burden of achieving a scientific target. The change will also save money, Hertz explains. Hertz says exoplanet researchers shouldn't worry about the proposed changes. "We know we'll get good science out of the coronagraph. We'll be able to see debris disks, zodiacal dust, and exoplanets in wide orbits," he says. Astronomers wanting to see Earth twins in the habitable zone may be disappointed, however.


Original Submission

Launch of James Webb Space Telescope Could be Further Delayed 33 comments

The Government Accountability Office (GAO) is warning of possible further delays to the launch of the James Webb Space Telescope (JWST):

A government watchdog is warning that the launch of the James Webb Space Telescope (JWST), the long-awaited successor to the Hubble that's been beset by schedule snafus and cost overruns, might face further delays. NASA announced in September it had pushed back the launch date of the JWST from late 2018 to some time in the spring of 2019 due to testing delays partly blamed on Hurricane Harvey's impact on Texas' Gulf Coast in August.

On Wednesday, lawmakers on the House Science, Space and Technology Committee were told it could take even longer to launch the world's most powerful telescope. "More delays are possible given the risks associated with the work ahead and the level of schedule reserves that are now (below) what's recommended," said Cristina Chaplain, director of Acquisition and Sourcing Management for the Government Accountability Office.

[...] Thomas Zurbuchen, NASA's associate administrator for science missions, told lawmakers he expects the space agency will be able to meet the spring 2019 schedule. "I believe it's achievable," he said.

Previously: James Webb Space Telescope Vibration Testing Completed
Launch of James Webb Space Telescope Delayed to Spring 2019

Related: Maiden Flight of the Space Launch System Delayed to 2019
NASA Unlikely to Have Enough Plutonium-238 for Missions by the Mid-2020s
WFIRST Space Observatory Could be Scaled Back Due to Costs


Original Submission

JWST: Too Big to Fail? 85 comments

The James Webb Space Telescope (JWST), an infrared space observatory with an $8.8 billion budget, will be transported to South America to launch atop an Ariane 5 rocket, presumably in Spring 2019. The JWST was not intended to be serviceable at the Earth-Sun L2 point. Will there still be a "Golden Age of astronomy" even if the JWST fails?

[Due] to its steadily escalating cost and continually delayed send-off (which recently slipped from 2018 to 2019), this telescopic time machine is now under increasingly intense congressional scrutiny. To help satisfy any doubts about JWST's status, the project is headed for an independent review as soon as January 2018, advised NASA's science chief Thomas Zurbuchen during an early December congressional hearing. Pressed by legislators about whether JWST will actually launch as presently planned in spring of 2019, he said, "at this moment in time, with the information that I have, I believe it's achievable."

[...] Simply launching JWST is fraught with peril, not to mention unfurling its delicate sunshield and vast, segmented mirror in deep space. Just waving goodbye to JWST atop its booster will be a nail-biter. "The truth is, every single rocket launch off of planet Earth is risky. The good news is that the Ariane 5 has a spectacular record," says former astronaut John Grunsfeld, a repeat "Hubble hugger" who made three space-shuttle visits to low-Earth orbit to renovate that iconic facility. Now scientist emeritus at NASA's Goddard Space Flight Center in Maryland, he sees an on-duty JWST as cranking out science "beyond all of our expectations."

"Assuming we make it to the injection trajectory to Earth-Sun L2, of course the next most risky thing is deploying the telescope. And unlike Hubble we can't go out and fix it. Not even a robot can go out and fix it. So we're taking a great risk, but for great reward," Grunsfeld says.

GAO: James Webb Space Telescope Launch Date Likely Will be Delayed (Again) 16 comments

The U.S. Government Acountability [sic] Office (GAO) has warned that the launch of James Webb Space Telescope (JWST) is likely to be delayed again, which could cause the budget cap set by the U.S. Congress to be exceeded:

The U.S. Government Acountability [sic] Office (GAO), a non-partisan group that investigates federal spending and performance, has issued a report on the James Webb Space Telescope that has astronomers worried. "It's likely the launch date will be delayed again," the report concludes — an ominous statement, given that any further delays could risk project cancellation.

Last year NASA announced a delay in the telescope's launch to sometime between March and June 2019. The 5- to 8-month delay came from problems integrating spacecraft components, especially its complex, five-layered sunshield, which must unfold perfectly when the telescope is deployed. Right after requesting the change in launch readiness date, the mission learned of further delays from its contractor, Northrum Grumman, due to "lessons learned from conducting deployment exercises of the spacecraft element and sunshield."

The mission now has 1.5 months of schedule reserve remaining, the GAO finds. Delays during integration and testing are common, "the phase in development where problems are most likely to be found and schedules tend to slip." The project has a total of five phases of integration and testing, and has made significant progress on phases three and four, with the fifth phase beginning in July.

GAO's 31-page report, February 2018: JWST: Integration and Test Challenges Have Delayed Launch and Threaten to Push Costs Over Cap.

Also at Science Magazine.

Previously: Launch of James Webb Space Telescope Delayed to Spring 2019
Launch of James Webb Space Telescope Could be Further Delayed

Related: James Webb Space Telescope Vibration Testing Completed
NASA Considering Flagship Space Telescope Options for the 2030s
WFIRST Space Observatory Could be Scaled Back Due to Costs
JWST: Too Big to Fail?
Trump Administration Budget Proposal Would Cancel WFIRST


Original Submission

Launch of James Webb Space Telescope Delayed to May 2020, Could Exceed Budget Cap 33 comments

The launch of the James Webb Space Telescope (JWST) has been delayed yet again, due to damage to the spacecraft's thrusters, sunshield, and tension cables:

The slip is not exactly surprising, even though construction and testing of Webb's primary mirror and scientific instruments—its riskiest, most expensive elements—is already complete. These components were delivered in early February to Webb's prime contractor, the aerospace company Northrop Grumman, for further testing and integration with the rest of the telescope. But later that month a report from the Government Accountability Office warned that the company had fallen behind schedule on the supposedly easier parts of the observatory. Valves on the spacecraft's thrusters had sprung leaks after being improperly cleaned, and replacing them had taken the better part of a year. Webb's tennis-court-sized, five-layered folding "sunshield" had also been torn during a test as it unfurled, requiring time-consuming failure analyses and repairs.

Screws and Washers Have Fallen Off JWST Amid Testing and Independent Review 32 comments

JWST suffers new problem during spacecraft testing

In a presentation at a meeting of the National Academies' Space Studies Board here May 3, Greg Robinson, the JWST program director at NASA Headquarters, said some "screws and washers" appear to have come off the spacecraft during recent environmental testing at a Northrop Grumman facility in Southern California. Technicians found the items after the spacecraft element of JWST, which includes the bus and sunshield but not its optics and instruments, was moved last weekend from one chamber for acoustics tests to another to prepare for vibration testing.

"Right now we believe that all of this hardware — we're talking screws and washers here — come from the sunshield cover," he said. "We're looking at what this really means and what is the recovery plan." The problem, he said, was only a couple of days old, and he had few additional details about the problem. "It's not terrible news, but it's not good news, either," he said. The incident, Robinson argued, showed the importance of the wide range of tests the spacecraft is put through prior to launch. "That's why we do the testing," he said. "We do it now, we find it now, we fix it and we launch a good spacecraft."

This latest incident comes as an independent review board, chartered by NASA in late March after announcing a one-year delay in JWST's launch because of other technical issues, is in the midst of its analysis of the mission and its launch readiness. That review, led by retired aerospace executive and former NASA Goddard director Tom Young, is scheduled to be completed at the end of the month.

NASA is expected to brief Congress on the status of the James Webb Space Telescope in late June.

Also at Popular Mechanics.

Previously: James Webb Space Telescope Vibration Testing Completed
Launch of James Webb Space Telescope Delayed to Spring 2019
JWST: Too Big to Fail?
GAO: James Webb Space Telescope Launch Date Likely Will be Delayed (Again)
Launch of James Webb Space Telescope Delayed to May 2020, Could Exceed Budget Cap
NASA Announces JWST Independent Review Board Members

Related: Northrop Grumman's Faulty Payload Adapter Reportedly Responsible for "Zuma" Failure


Original Submission

Launch of James Webb Space Telescope Delayed Again, This Time to March 2021, Cost at $9.66 Billion 17 comments

Remember the JWST? Yup:

NASA has again delayed the launch of its next-generation space observatory, known as the James Webb Space Telescope (JWST), the space agency announced today. The telescope now has a new launch date of March 30th, 2021. It's the second delay to the project's timeline this year, and the third in the last nine months.

"We're all disappointed that the culmination of Webb and its launch is taking longer than expected, but we're creating something new here. We're dealing with cutting edge technology to perform an unprecedented mission, and I know that our teams are working hard and will successfully overcome the challenges," NASA Administrator Jim Bridenstine said in a video statement. "In space we always have to look at the long term, and sometimes the complexities of our missions don't come together as soon as we wish. But we learn, we move ahead, and ultimately we succeed."

NASA pushed the launch of JWST, which is viewed as a more powerful successor to the Hubble Space Telescope, from 2019 to 2020 in March of this year. At the same time the space agency also convened an independent review board to assess the future of the project, which is running the risk of blowing by an $8 billion cost cap set by NASA in 2011. Going beyond that cost cap would mean that Congress has to reauthorize the program.

JWST Launch Christmas Morning 55 comments

James Webb Space Telescope reaches launch pad for Christmas liftoff

The James Webb Space Telescope is due to launch on Saturday (Dec. 25) during a 32-minute window that opens at 7:20 a.m. EST (1220 GMT). The massive observatory will blast off from Kourou, French Guiana, atop an Ariane 5 rocket operated by European launch provider Arianespace. You can watch launch coverage live at Space.com beginning at 6 a.m. EST (1100 GMT) courtesy of NASA or you can watch directly at the agency's website.

ESA launch kit (PDF).

Previously:


Original Submission

This discussion has been archived. No new comments can be posted.
Display Options Threshold/Breakthrough Mark All as Read Mark All as Unread
The Fine Print: The following comments are owned by whoever posted them. We are not responsible for them in any way.
(1)
  • (Score: 1) by rylyeh on Monday October 02 2017, @04:54AM (6 children)

    by rylyeh (6726) <kadathNO@SPAMgmail.com> on Monday October 02 2017, @04:54AM (#575762)

    Damm!

    Of course, this all must be done properly but just - Damm!

    --
    "a vast crenulate shell wherein rode the grey and awful form of primal Nodens, Lord of the Great Abyss."
    • (Score: 2) by takyon on Monday October 02 2017, @05:06AM

      by takyon (881) <takyonNO@SPAMsoylentnews.org> on Monday October 02 2017, @05:06AM (#575768) Journal

      It's a blow.

      At least there is no way to delay the Jan. 1, 2019 New Horizons flyby of 2014 MU69 [wikipedia.org].

      --
      [SIG] 10/28/2017: Soylent Upgrade v14 [soylentnews.org]
    • (Score: 4, Interesting) by julian on Monday October 02 2017, @06:36AM (4 children)

      by julian (6003) Subscriber Badge on Monday October 02 2017, @06:36AM (#575784)

      Ariane 5 has a 95.7% success rate. That's pretty good for rocket launches, but the James Webb has been in development since 1996. That's a long time to spend on something that could go BOOM 1/20 times.

      I am glad that they are minimizing the problems they can control. We don't want any extra problems added to the Ariane 5 launch risk.

      JWST should be a revolution in astronomy. I'm very excited for the decade of science beginning in 2020. With the new Hawaiian 30-meter telescope finally moving forward we should be learning some amazing things in the first half of the 21st century.

      • (Score: 3, Interesting) by aiwarrior on Monday October 02 2017, @07:19AM

        by aiwarrior (1812) on Monday October 02 2017, @07:19AM (#575793) Journal

        While i agree with you, I also think that a lot of the time spent is one-time effort, which in case of a boom, would not need to be repeated. Of course it would delay perhaps 1 or 2 years but it would not start all over again.

        Regardless, go go James Webb

      • (Score: 2) by acid andy on Monday October 02 2017, @11:24AM (2 children)

        by acid andy (1683) on Monday October 02 2017, @11:24AM (#575855) Homepage Journal

        Shame they couldn't afford to build two of everything. That way they'd have a backup.

        --
        If a cat has kittens, does a rat have rittens, a bat bittens and a mat mittens?
        • (Score: 0) by Anonymous Coward on Monday October 02 2017, @12:53PM (1 child)

          by Anonymous Coward on Monday October 02 2017, @12:53PM (#575874)

          First rule of government spending: why buy one when you can have two for twice the price?

          Otoh, in that movie, having two for twice the price saved the day.

          • (Score: 2) by acid andy on Monday October 02 2017, @01:13PM

            by acid andy (1683) on Monday October 02 2017, @01:13PM (#575878) Homepage Journal

            Otoh, in that movie, having two for twice the price saved the day.

            Yeah, I guess that's partly what I was thinking of.

            --
            If a cat has kittens, does a rat have rittens, a bat bittens and a mat mittens?
  • (Score: 2) by bob_super on Monday October 02 2017, @07:10PM (1 child)

    by bob_super (1357) on Monday October 02 2017, @07:10PM (#576099)

    I know that we need it supercooled for the infrared science we need, and away from the planet and the infrared it radiates.
    But dang, that seems like such a shame to spend so much time and money building such a cool toy, and not have a way to refuel the coolant, or switch it to visible afterwards.

    A lot of spacecrafts don't even do science for 5 years for sure, but we're Hubblespoiled.

    • (Score: 2) by takyon on Monday October 02 2017, @07:37PM

      by takyon (881) <takyonNO@SPAMsoylentnews.org> on Monday October 02 2017, @07:37PM (#576128) Journal

      Unclear (to me):

      • While JWST was not designed to be easily serviced by astronauts or robotic craft, and is much further away than Hubble, could it still be serviced by either method if we chose to do so?
      • Will JWST be permanently damaged once coolant runs out? ie. If we refill the coolant, propellant, and replace batteries in 20 years, will it still be unusable?
      • Would the JWST's eventual drift from the L2 point once it runs out of propellant permanently prevent the craft from being useful or reachable?
      • Can JWST operate in the near-infrared even after coolant runs out?
      • Is the 5-10 year lifetime estimate yet another conservative NASA estimate? Example: the Opportunity rover has lasted over 13 years instead of 90 days.

      https://en.wikipedia.org/wiki/James_Webb_Space_Telescope#Comparisons [wikipedia.org]

      However, infrared telescopes have an Achilles heel—they need to stay extremely cold, and the longer the wavelength of infrared, the colder they need to be.[45] If not, the background heat of the device itself overwhelms the detectors, making it effectively blind.[45] This can be overcome by careful spacecraft design, in particular by placing the telescope in dewar with an extremely cold substance, such as liquid helium.[45] This has meant most infrared telescopes have a lifespan limited by their coolant, as short as a few months, maybe a few years at most.[45] It has been possible to maintain a temperature low enough through the design of the spacecraft to enable near-infrared observations without a supply of coolant, such as the extended missions of Spitzer or NEOWISE. Another example is Hubble's NICMOS instrument, which started out using a block of nitrogen ice that depleted after a couple years, but was then converted to a cryocooler that worked continuously. The James Webb Space Telescope is designed to cool itself without a dewar, using a combination of sun-shield and radiators with the mid-infrared instrument using an additional cryocooler.[46]

      --
      [SIG] 10/28/2017: Soylent Upgrade v14 [soylentnews.org]
(1)