According to an article at Snopes.com:
The Army Corps of Engineers has denied the easement needed to complete the Dakota Access Pipeline, according Colonel Henderson, who notified Veterans for Standing Rock co-organizer Michael A. Wood Jr on 4 December 2016.
More than 3,000 veterans had converged at the Standing Rock camp to support the Sioux in their ongoing opposition to the building of a $3.7 billion pipeline that would cross through disputed land managed by the Army Corps of Engineers. Wood said upon learning of the move, "This is history."
From a report in Al Jazeera :
The US Army Corps of Engineers has turned down a permit for a controversial pipeline project running through North Dakota, in a victory for Native Americans and climate activists who have protested against the project for several months, according to a statement released.
The 1,885km Dakota Access Pipeline, owned by Texas-based Energy Transfer Partners LP, had been complete except for a segment planned to run under Lake Oahe, a reservoir formed by a dam on the Missouri River.
"The Army will not grant an easement to cross Lake Oahe at the proposed location based on the current record," a statement from the US Army said.
The Standing Rock Sioux tribe, along with climate activists, have been protesting the $3.8bn project, saying it could contaminate the water supply and damage sacred tribal lands.
[...] "Today, the US Army Corps of Engineers announced that it will not be granting the easement to cross Lake Oahe for the proposed Dakota Access Pipeline," said Standing Rock Chairman Dave Archambault II, in a statement.
"Instead, the Corps will be undertaking an environmental impact statement to look at possible alternative routes."
(Score: 0) by Anonymous Coward on Monday December 05 2016, @04:42PM
> of course Obama gives them everything they want.... while everyone knows the block will only hold a few weeks. So why do it? So Trump will own it,
Grow up.
The Corps initiated the review months ago, back when Obama clearly expected Clinton to win.
http://www.npr.org/sections/thetwo-way/2016/09/09/493280504/judge-rules-that-construction-can-proceed-on-dakota-access-pipeline [npr.org]
the Justice Department, the Department of the Army and the Interior Department announced that construction in an area of Army Corps' land that is particularly significant to the tribe will not go forward pending further evaluation.
"The Army will not authorize constructing the Dakota Access pipeline on Corps land bordering or under Lake Oahe until it can determine whether it will need to reconsider any of its previous decisions regarding the Lake Oahe site under the National Environmental Policy Act (NEPA) or other federal laws," the statement read.
The agencies asked the pipeline company to "voluntarily pause all construction activity within 20 miles east or west of Lake Oahe."