The James Webb Space Telescope (JWST) remains on track for an October 2018 launch:
JWST passed its final vibration testing Tuesday ensuring that the craft is finally fit for spaceflight. NASA has scheduled the telescope for an October 2018 launch, but the telescope was originally supposed to be launched in 2011 marking a long history of major cost overruns and delays.
NASA announced last December that the JWST was halfway completed, but the project is currently $7.2 billion over its initial budget and seven years behind the original schedule. The JWST was initially projected to cost $1.6 billion. The Government Accountability Office (GAO) now estimates the final cost of the telescope at $8.8 billion.
[...] During vibration testing in December at NASA's Goddard Spaceflight Center, accelerometers attached to the telescope detected "unexpected responses" and engineers were forced to shut the test down to protect the hardware. The kind of response NASA found could potentially create serious problems when the telescope is launched into space.
Related Stories
The Government Accountability Office (GAO) is warning of possible further delays to the launch of the James Webb Space Telescope (JWST):
A government watchdog is warning that the launch of the James Webb Space Telescope (JWST), the long-awaited successor to the Hubble that's been beset by schedule snafus and cost overruns, might face further delays. NASA announced in September it had pushed back the launch date of the JWST from late 2018 to some time in the spring of 2019 due to testing delays partly blamed on Hurricane Harvey's impact on Texas' Gulf Coast in August.
On Wednesday, lawmakers on the House Science, Space and Technology Committee were told it could take even longer to launch the world's most powerful telescope. "More delays are possible given the risks associated with the work ahead and the level of schedule reserves that are now (below) what's recommended," said Cristina Chaplain, director of Acquisition and Sourcing Management for the Government Accountability Office.
[...] Thomas Zurbuchen, NASA's associate administrator for science missions, told lawmakers he expects the space agency will be able to meet the spring 2019 schedule. "I believe it's achievable," he said.
Previously: James Webb Space Telescope Vibration Testing Completed
Launch of James Webb Space Telescope Delayed to Spring 2019
Related: Maiden Flight of the Space Launch System Delayed to 2019
NASA Unlikely to Have Enough Plutonium-238 for Missions by the Mid-2020s
WFIRST Space Observatory Could be Scaled Back Due to Costs
The U.S. Government Acountability [sic] Office (GAO) has warned that the launch of James Webb Space Telescope (JWST) is likely to be delayed again, which could cause the budget cap set by the U.S. Congress to be exceeded:
The U.S. Government Acountability [sic] Office (GAO), a non-partisan group that investigates federal spending and performance, has issued a report on the James Webb Space Telescope that has astronomers worried. "It's likely the launch date will be delayed again," the report concludes — an ominous statement, given that any further delays could risk project cancellation.
Last year NASA announced a delay in the telescope's launch to sometime between March and June 2019. The 5- to 8-month delay came from problems integrating spacecraft components, especially its complex, five-layered sunshield, which must unfold perfectly when the telescope is deployed. Right after requesting the change in launch readiness date, the mission learned of further delays from its contractor, Northrum Grumman, due to "lessons learned from conducting deployment exercises of the spacecraft element and sunshield."
The mission now has 1.5 months of schedule reserve remaining, the GAO finds. Delays during integration and testing are common, "the phase in development where problems are most likely to be found and schedules tend to slip." The project has a total of five phases of integration and testing, and has made significant progress on phases three and four, with the fifth phase beginning in July.
GAO's 31-page report, February 2018: JWST: Integration and Test Challenges Have Delayed Launch and Threaten to Push Costs Over Cap.
Also at Science Magazine.
Previously: Launch of James Webb Space Telescope Delayed to Spring 2019
Launch of James Webb Space Telescope Could be Further Delayed
Related: James Webb Space Telescope Vibration Testing Completed
NASA Considering Flagship Space Telescope Options for the 2030s
WFIRST Space Observatory Could be Scaled Back Due to Costs
JWST: Too Big to Fail?
Trump Administration Budget Proposal Would Cancel WFIRST
JWST suffers new problem during spacecraft testing
In a presentation at a meeting of the National Academies' Space Studies Board here May 3, Greg Robinson, the JWST program director at NASA Headquarters, said some "screws and washers" appear to have come off the spacecraft during recent environmental testing at a Northrop Grumman facility in Southern California. Technicians found the items after the spacecraft element of JWST, which includes the bus and sunshield but not its optics and instruments, was moved last weekend from one chamber for acoustics tests to another to prepare for vibration testing.
"Right now we believe that all of this hardware — we're talking screws and washers here — come from the sunshield cover," he said. "We're looking at what this really means and what is the recovery plan." The problem, he said, was only a couple of days old, and he had few additional details about the problem. "It's not terrible news, but it's not good news, either," he said. The incident, Robinson argued, showed the importance of the wide range of tests the spacecraft is put through prior to launch. "That's why we do the testing," he said. "We do it now, we find it now, we fix it and we launch a good spacecraft."
This latest incident comes as an independent review board, chartered by NASA in late March after announcing a one-year delay in JWST's launch because of other technical issues, is in the midst of its analysis of the mission and its launch readiness. That review, led by retired aerospace executive and former NASA Goddard director Tom Young, is scheduled to be completed at the end of the month.
NASA is expected to brief Congress on the status of the James Webb Space Telescope in late June.
Also at Popular Mechanics.
Previously: James Webb Space Telescope Vibration Testing Completed
Launch of James Webb Space Telescope Delayed to Spring 2019
JWST: Too Big to Fail?
GAO: James Webb Space Telescope Launch Date Likely Will be Delayed (Again)
Launch of James Webb Space Telescope Delayed to May 2020, Could Exceed Budget Cap
NASA Announces JWST Independent Review Board Members
Related: Northrop Grumman's Faulty Payload Adapter Reportedly Responsible for "Zuma" Failure
James Webb Space Telescope reaches launch pad for Christmas liftoff
The James Webb Space Telescope is due to launch on Saturday (Dec. 25) during a 32-minute window that opens at 7:20 a.m. EST (1220 GMT). The massive observatory will blast off from Kourou, French Guiana, atop an Ariane 5 rocket operated by European launch provider Arianespace. You can watch launch coverage live at Space.com beginning at 6 a.m. EST (1100 GMT) courtesy of NASA or you can watch directly at the agency's website.
ESA launch kit (PDF).
Previously:
Space science: The telescope that ate astronomy
JWST Primary Mirror Starting To Come Together
New Space Telescope's Giant Gold Mirror Unveiled (April 29th)
Telescope That 'Ate Astronomy' Is on Track to Surpass Hubble
James Webb Space Telescope Vibration Testing Completed
Launch of James Webb Space Telescope Delayed to Spring 2019
Launch of James Webb Space Telescope Could be Further Delayed
JWST: Too Big to Fail?
GAO: James Webb Space Telescope Launch Date Likely Will be Delayed (Again)
Launch of James Webb Space Telescope Delayed to May 2020, Could Exceed Budget Cap
NASA Announces JWST Independent Review Board Members
Screws and Washers Have Fallen Off JWST Amid Testing and Independent Review
Launch of James Webb Space Telescope Delayed Again, This Time to March 2021, Cost at $9.66 Billion
NASA Administrator at House Hearing: WFIRST Could be Delayed to Help Pay for JWST
James Webb Passes Critical Mission Review for 2021 Launch, Final Testing Nearing Completion
NASA Ominously Chooses Halloween 2021 to Launch Long-Delayed Space Telescope
The James Webb Space Telescope, NASA's Next Great Observatory, Passes Final Ground Tests
The James Webb Telescope has a Launch Date
NASA's James Webb Space Telescope Passes Crucial Launch-Simulation Tests
James Webb Telescope: Preparations Resume for December 22 Launch
NASA's James Webb Space Telescope Fully Fueled for Launch
(Score: 0) by Anonymous Coward on Thursday March 30 2017, @12:13PM (2 children)
This time, the fucking JWST cunt was satisfied with the vibrator.
Damn'd time she was, after $8.8B thrown up her arse.
(Score: 2) by stormwyrm on Thursday March 30 2017, @03:09PM (1 child)
The US government almost ruined the JWST, and blamed NASA for it. [scienceblogs.com]
I’m only glad that it’s finally getting finished.
Numquam ponenda est pluralitas sine necessitate.
(Score: 2) by bob_super on Thursday March 30 2017, @04:27PM
It's NASA's fault.
If they had designed a telescope which can be used to find oil or spy on people, the NRO's copy would have been launched on time and on budget!
(Score: 0) by Anonymous Coward on Thursday March 30 2017, @12:22PM (1 child)
Nice selection of clickbait and scam ads on that site.
(Score: 2, Informative) by Anonymous Coward on Thursday March 30 2017, @01:38PM
Daily Caller, Phys.org, etc. Don't know why out of all those links, there isn't one to the actual NASA site with the news [nasa.gov].